There's a rumor floating around that the Kansas Avenue railroad overpass project has fallen through, or something to that effect.
I called City Manager Steve Archer today to ask him about it, but I was pretty sure I already knew what his answer would be.
In short, there's nothing to it. The project is proceeding as expected.
The start of construction was moved back to January, so perhaps that's where this rumor got started. This is pretty normal for KDOT lately, because they're swamped trying to get all of the stimulus projects done before the end of the year.
To make a long story short: The overpass will begin in January. Once the dirt ramps are built, they have to sit for six months with no settling before the bridge can be built.
Also, Archer told me the money that has been appropriated can't be spent on anything else anyway, so there's little to no chance KDOT would kill the project at this point.